TSS

Data Centre 1, Dublin, Ireland

  • Dublin,Ireland
  • 3 years
  • Confidential
  • €8,000,000
SERVICES
ICT Services

Mercury were contracted to undertake all the ICT Fibre & Copper Installation for this Hyperscale Data Centre. The Data Centre includes a total of 12 halls across 3 separate buildings.

The scope of work includes the Installation & Commissioning of the following:

  • 244 kms of Fibre Backbone to support Building Systems and link into existing campus MDFs. Splice on site.
  • 26 kms of 864 core fibre cabling linking Colo IDFs to MDFs between buildings on Campus. MTP to Splice
  • 48 kms of 144 core fibre linking MDFs. MTP to MTP
  • 216 kms of 288 core fibre Internal Colo Links. MTP to MTP
  • 9 kms of Fibre Runner including various Dropouts
  • Cat 6 & Cat 6A copper cabling supporting various applications
  • Rack and Cabinet Installation in MDFs, IDFs and Server Rows

The scope of this project includes the complete IT Infrastructure and campus backbone for the full build out of a three building, twelve hall campus with a 60 MW capacity and the total floor of the completed buildings is approx. 56,000 Sq. m. Mercury continue to support our client on IT infrastructure projects across Europe.

The scope of this project includes the complete IT Infrastructure and campus backbone for the full build out of a three building, twelve hall campus.