Woking Data Centre

  • Following the success of previous Projects with Sentrum, Mercury successfully negotiated the contract to provide a complete turnkey package to this facility  including full design, Civil, structural, Architectural, Electrical, Mechanical, Structured Cabling and Fire Suppression systems.

 

  • This project involved converting an existing warehouse measuring 167m x 100m.

 

  • The scope includes erecting 2 new Internal floors independent of the existing structure, removal of the roof and creation of a Chiller well, extensive Civil works for a 90MW Sub-station, acoustic screening,  high security SEAP Fencing and truck barriers.

 

  • All this work was carried out on a strict noise criteria as there were adjacent residences.

 

  • All CSA works were managed by Mercury’s project management team.

Testimonial

“Provided excellent service, were team players and provided valuable input into this highly complex facility.”

Woking, United Kingdom

€ 115,000,000 (£ 96m)

  • 30 months

  • Multidisciplinary
  • Mechanical
  • Electrical
  • Fire Protection
  • Design
  • Turnkey Construction