Enterprise Data Centres

LD10.2 Data Centre, London, UK

Mercury was awarded this contract after successfully completing previous projects with this repeat client in London.

The scope of work of this project included:

• The formation of a mezzanine floor slab across 50% of the existing open plan warehouse

• 4 3Mw data halls and associated switch rooms; above and below the mezzanine floor

• 4 new switch rooms forming Rope 1 of the electrical distribution network, compromising of HV cast retain transformers, LV input board, UPS and associated batteries and UPS output board

• The installation of new HV Switch rooms and distribution networks from the upgraded SSE 33/11KV substation

• The formation of a new external steel gantry to enable 6 2.5MVA HV generator sets and associated bulk fuel stores to be installed

• The installation of a processed treated water plant and associated water storage tanks, to provide 24-hour standby water supplies to the Jaeggi HDACs

• The chilled water distribution via carbon steel pipework in a ring configuration with risers dropping from the lid level to the lower floor voids

• The installation of water mist systems in all Data Halls and sprinklers in storage rooms.

This was a highly rewarding and challenging project of which Mercury successfully met all requirements.

SERVICES
Contracting
  • London,UK
  • 12 months
  • Confidential
  • €20,000,000