Dell

DELL’s production plant in Tódź is one of the most advanced Dell factories in the world, and the second Dell factory in Europe. This 5.5ha facility located on a 27ha area, includes the EMF4 building, site infrastructure, and a tier IV Data Centre.

Mercury Engineering executed mechanical, fire protection, electrical, and low voltage services. Works included M&E services including process, fire detection and suppression, as well as Data Center critical systems.

Services

Mechanical
Electrical
Low Voltage

Challenges

Our team of professional and experienced engineers ensured that this fast track project was delivered in record time.

Testimonials

“Mercury Engineering completed above works professionally, according to current quality and works organization standards. Commitment and good understanding of the project resulted [in] completion of works … 14 days before the deadline.”

Andy Cunningham
Dell EMEA Senior Project Manager

Lódź, Poland

€ 17,500,000

  • 9 months

  • Multidisciplinary
  • Mechanical
  • Electrical