Data Electronics

Mercury installed a new generator externally at first floor level which was supported on a structural steel framework and housed within a cladding enclosure.

Upgraded the M&E infrastructure of Telecity’s facility.

Removed existing plant (chillers & AHU’s) and replaced same with new equipment at roof level.

Removed and replaced flow-forge flooring , also removed cladding to allow access for construction/delivery of large kit items.

Constructed new roof access to the plant area via the internal stair core, including a new roof access door and elevated enclosure.

Dublin, Ireland

€ 2,700,000

  • 5 months

  • Multidisciplinary
  • Mechanical
  • Electrical
  • Turnkey Construction