Blood Transfusion Services Board

  • This fast track project involved the construction of new laboratories and administration offices for new BTSB Headquarters.

 

  • Mercury carried out the complete electrical services including the fit-out of 4,000m2 highly serviced cleanroom labs and 6,000m2 of administration space.

 

  • The Labs were built to adhere to cleanroom protocol requiring substantial plant and the integration of sealed air handling units.

 

  • The works required intensive co-ordination and minimum interference with the day-to-day operation of one of Irelands busiest Hospitals.

Dublin, Ireland

€4,450,000

  • 16 Months

  • Electrical