This first Biogas power plant in the Wielkopolska region was erected in 2010. The project involved the construction of a 526 kW power plant and was co-financed by the EU Cohesion Fund under the Infrastructure and Environment Operational Program.
Scope of Mercury works included execution of mechanical, teletechnical, and BMS services.

Services

Mechanical services
Teletechnical services
BMS

Innovation

The innovation and originality of the technology comes from the combination of recycling processes and highly efficient production of renewable energy. Combined heat and power generation plant was a first of its type installed by Mercury in Poland.

Skrzatusz, Poland

€ 1,000,000

  • 9 months

  • Mechanical