{"id":8600,"date":"2022-07-13T10:34:34","date_gmt":"2022-07-13T10:34:34","guid":{"rendered":"https:\/\/www.mercuryeng.com\/?p=8600"},"modified":"2022-07-13T10:42:47","modified_gmt":"2022-07-13T10:42:47","slug":"optimizing-data-centre-project-planning-with-4d-bim-modelling","status":"publish","type":"post","link":"https:\/\/www.mercuryeng.com\/de\/2022\/07\/13\/optimizing-data-centre-project-planning-with-4d-bim-modelling\/","title":{"rendered":"Optimizing data centre project planning with 4D BIM modelling"},"content":{"rendered":"<p>Mercury recently delivered two data centre projects, while utilizing <strong>4D BIM modeling<\/strong>, enabling our team to optimize project planning, while eliminating potential risks from outset.<\/p>\n<p>The use of digital technology was central to our successful completion of these two projects.<\/p>\n<p>As the prime contractor, Mercury was responsible for the design, through to handover, with our team overcoming a number of unique challenges, including a relatively short construction programme of eight months.<\/p>\n<p>Recent technological advancements have resulted in the ability to introduce a 4<sup>th<\/sup> dimension into our BIM model \u2013 time.<\/p>\n<p>Our multi-national client requested the most up-to-date progress data, and we introduced SYNCHRO 4D by Bentley, which integrates the project schedule with the construction model.<\/p>\n<figure id=\"attachment_8601\" aria-describedby=\"caption-attachment-8601\" style=\"width: 1000px\" class=\"wp-caption aligncenter\"><img loading=\"lazy\" decoding=\"async\" class=\"wp-image-8601 size-large\" src=\"\/wp-content\/uploads\/2022\/07\/Picture1-1000x750.jpg\" alt=\"\" width=\"1000\" height=\"750\" srcset=\"https:\/\/www.mercuryeng.com\/wp-content\/uploads\/2022\/07\/Picture1-1000x750.jpg 1000w, https:\/\/www.mercuryeng.com\/wp-content\/uploads\/2022\/07\/Picture1-350x263.jpg 350w, https:\/\/www.mercuryeng.com\/wp-content\/uploads\/2022\/07\/Picture1-700x525.jpg 700w, https:\/\/www.mercuryeng.com\/wp-content\/uploads\/2022\/07\/Picture1.jpg 1400w\" sizes=\"auto, (max-width: 1000px) 100vw, 1000px\" \/><figcaption id=\"caption-attachment-8601\" class=\"wp-caption-text\">Stock photo: Building Information Model of metal structure.<\/figcaption><\/figure>\n<p>Through SYNCHRO, our planning team developed a 4D model of the project, which accurately highlights progress throughout the timeline. We also noted benefits in increased scheduling accuracy and streamlined communication, as required for these complex projects.<\/p>\n<p>Additionally, the Mercury team and project stakeholders could review and edit construction tasks in an immersive environment, pushing digital construction to the edge.<\/p>\n<p>SYNCHRO 4D\u2019s planning and simulation allowed our team to foresee potential clashes in the digital environment, which positioned us to find alternative solutions to challenges faced.<\/p>\n<p>In addition, this software also supports a more efficient handover of the model for the next stage of the project. This developed further, our visual planning, automated quantity takeoff and reduced project risk delays, and time-consuming rework.<\/p>\n<p>Andrew Valette, Senior Project Planner said: \u201cOur client expressed an interest in utilizing 4D modelling on these two projects and it was something we have successfully implemented previously. By using SYNCHRO, Mercury was able to illustrate the construction programme in a way that was easy to communicate with all parties. We conveyed pinch-points and issues to relevant stakeholders and were also able to better introduce our subcontractors to our processes, improving collaboration and efficiency.\u201d<\/p>\n<h3>DIGITAL EDGE<\/h3>\n<p>Synchro is an initiative of the \u2018Digital Edge\u2019 pillar from Mercury\u2019s\u00a0<a href=\"https:\/\/www.mercuryeng.com\/about-us\/our-strategy\/\">Beyond50<\/a>\u00a0strategy. The core goal of this pillar is to deliver a mobile, integrated digital backbone for back office and frontline workers from design through to operations that drives our digital project delivery to the edge. Read more about innovation in Mercury\u00a0<a href=\"https:\/\/www.mercuryeng.com\/about-us\/innovation\">here<\/a>.<\/p>\n<p>Like Mercury on\u00a0<a href=\"https:\/\/www.facebook.com\/MercuryEngineering\/\">Facebook.<\/a><\/p>\n<p>Follow us on\u00a0<a href=\"https:\/\/www.linkedin.com\/company\/mercury-engineering\/\">LinkedIn<\/a>,\u00a0<a href=\"https:\/\/twitter.com\/mercuryeng\">Twitter<\/a>\u00a0and\u00a0<a href=\"https:\/\/www.instagram.com\/mercuryengineering\/\">Instagram.<\/a><\/p>\n","protected":false},"excerpt":{"rendered":"<p>Mercury recently delivered two data centre projects, while utilizing 4D BIM modeling, enabling our team to optimize project planning, while eliminating potential risks from outset. The use of digital technology was central to our successful completion of these two projects. As the prime contractor, Mercury was responsible for the design, through to handover, with our [&hellip;]<\/p>\n","protected":false},"author":17,"featured_media":8602,"comment_status":"closed","ping_status":"closed","sticky":false,"template":"","format":"standard","meta":{"_acf_changed":false,"footnotes":""},"categories":[1,34],"class_list":["post-8600","post","type-post","status-publish","format-standard","has-post-thumbnail","hentry","category-mercury-engineering","category-design-quality-innovation"],"acf":[],"yoast_head":"<!-- This site is optimized with the Yoast SEO plugin v28.7 - https:\/\/yoast.com\/product\/yoast-seo-wordpress\/ -->\n<title>Optimizing data centre project planning with 4D BIM modelling<\/title>\n<meta name=\"description\" content=\"Mercury delivered two data centre projects while utilizing 4D BIM modeling, enabling us to optimize project planning and eliminate risks.\" \/>\n<meta name=\"robots\" content=\"index, follow, max-snippet:-1, max-image-preview:large, max-video-preview:-1\" \/>\n<link rel=\"canonical\" href=\"https:\/\/www.mercuryeng.com\/de\/2022\/07\/13\/optimizing-data-centre-project-planning-with-4d-bim-modelling\/\" \/>\n<meta property=\"og:locale\" content=\"de_DE\" \/>\n<meta property=\"og:type\" content=\"article\" \/>\n<meta property=\"og:title\" content=\"Optimizing data centre project planning with 4D BIM modelling\" \/>\n<meta property=\"og:description\" content=\"Mercury recently delivered two data centre projects, while utilizing 4D BIM modeling, enabling our team to optimize project planning, while eliminating potential risks from outset.\" \/>\n<meta property=\"og:url\" content=\"https:\/\/www.mercuryeng.com\/de\/2022\/07\/13\/optimizing-data-centre-project-planning-with-4d-bim-modelling\/\" \/>\n<meta property=\"og:site_name\" content=\"Mercury Engineering\" \/>\n<meta property=\"article:published_time\" content=\"2022-07-13T10:34:34+00:00\" \/>\n<meta property=\"article:modified_time\" content=\"2022-07-13T10:42:47+00:00\" \/>\n<meta property=\"og:image\" content=\"https:\/\/www.mercuryeng.com\/wp-content\/uploads\/2022\/07\/feature-1.jpg\" \/>\n\t<meta property=\"og:image:width\" content=\"1430\" \/>\n\t<meta property=\"og:image:height\" content=\"953\" \/>\n\t<meta property=\"og:image:type\" content=\"image\/jpeg\" \/>\n<meta name=\"author\" content=\"Tiffany Zhou\" \/>\n<meta name=\"twitter:card\" content=\"summary_large_image\" \/>\n<meta name=\"twitter:title\" content=\"Optimizing data centre project planning with 4D BIM modelling\" \/>\n<meta name=\"twitter:description\" content=\"Mercury recently delivered two data centre projects, while utilizing 4D BIM modeling, enabling our team to optimize project planning, while eliminating potential risks from outset.\" \/>\n<meta name=\"twitter:image\" content=\"https:\/\/www.mercuryeng.com\/wp-content\/uploads\/2022\/07\/feature-1.jpg\" \/>\n<meta name=\"twitter:label1\" content=\"Verfasst von\" \/>\n\t<meta name=\"twitter:data1\" content=\"Tiffany Zhou\" \/>\n\t<meta name=\"twitter:label2\" content=\"Gesch\u00e4tzte Lesezeit\" \/>\n\t<meta name=\"twitter:data2\" content=\"2 Minuten\" \/>\n<script type=\"application\/ld+json\" class=\"yoast-schema-graph\">{\"@context\":\"https:\\\/\\\/schema.org\",\"@graph\":[{\"@type\":\"Article\",\"@id\":\"https:\\\/\\\/www.mercuryeng.com\\\/de\\\/2022\\\/07\\\/13\\\/optimizing-data-centre-project-planning-with-4d-bim-modelling\\\/#article\",\"isPartOf\":{\"@id\":\"https:\\\/\\\/www.mercuryeng.com\\\/de\\\/2022\\\/07\\\/13\\\/optimizing-data-centre-project-planning-with-4d-bim-modelling\\\/\"},\"author\":{\"name\":\"Tiffany Zhou\",\"@id\":\"https:\\\/\\\/www.mercuryeng.com\\\/de\\\/#\\\/schema\\\/person\\\/523c7a8c2fb2021a9ac2a44d26c5920e\"},\"headline\":\"Optimizing data centre project planning with 4D BIM modelling\",\"datePublished\":\"2022-07-13T10:34:34+00:00\",\"dateModified\":\"2022-07-13T10:42:47+00:00\",\"mainEntityOfPage\":{\"@id\":\"https:\\\/\\\/www.mercuryeng.com\\\/de\\\/2022\\\/07\\\/13\\\/optimizing-data-centre-project-planning-with-4d-bim-modelling\\\/\"},\"wordCount\":403,\"image\":{\"@id\":\"https:\\\/\\\/www.mercuryeng.com\\\/de\\\/2022\\\/07\\\/13\\\/optimizing-data-centre-project-planning-with-4d-bim-modelling\\\/#primaryimage\"},\"thumbnailUrl\":\"\\\/wp-content\\\/uploads\\\/2022\\\/07\\\/feature-1.jpg\",\"articleSection\":[\"News\",\"Design, Quality &amp; Innovation\"],\"inLanguage\":\"de-DE\"},{\"@type\":\"WebPage\",\"@id\":\"https:\\\/\\\/www.mercuryeng.com\\\/de\\\/2022\\\/07\\\/13\\\/optimizing-data-centre-project-planning-with-4d-bim-modelling\\\/\",\"url\":\"https:\\\/\\\/www.mercuryeng.com\\\/de\\\/2022\\\/07\\\/13\\\/optimizing-data-centre-project-planning-with-4d-bim-modelling\\\/\",\"name\":\"Optimizing data centre project planning with 4D BIM modelling\",\"isPartOf\":{\"@id\":\"https:\\\/\\\/www.mercuryeng.com\\\/de\\\/#website\"},\"primaryImageOfPage\":{\"@id\":\"https:\\\/\\\/www.mercuryeng.com\\\/de\\\/2022\\\/07\\\/13\\\/optimizing-data-centre-project-planning-with-4d-bim-modelling\\\/#primaryimage\"},\"image\":{\"@id\":\"https:\\\/\\\/www.mercuryeng.com\\\/de\\\/2022\\\/07\\\/13\\\/optimizing-data-centre-project-planning-with-4d-bim-modelling\\\/#primaryimage\"},\"thumbnailUrl\":\"\\\/wp-content\\\/uploads\\\/2022\\\/07\\\/feature-1.jpg\",\"datePublished\":\"2022-07-13T10:34:34+00:00\",\"dateModified\":\"2022-07-13T10:42:47+00:00\",\"author\":{\"@id\":\"https:\\\/\\\/www.mercuryeng.com\\\/de\\\/#\\\/schema\\\/person\\\/523c7a8c2fb2021a9ac2a44d26c5920e\"},\"description\":\"Mercury delivered two data centre projects while utilizing 4D BIM modeling, enabling us to optimize project planning and eliminate risks.\",\"breadcrumb\":{\"@id\":\"https:\\\/\\\/www.mercuryeng.com\\\/de\\\/2022\\\/07\\\/13\\\/optimizing-data-centre-project-planning-with-4d-bim-modelling\\\/#breadcrumb\"},\"inLanguage\":\"de-DE\",\"potentialAction\":[{\"@type\":\"ReadAction\",\"target\":[\"https:\\\/\\\/www.mercuryeng.com\\\/de\\\/2022\\\/07\\\/13\\\/optimizing-data-centre-project-planning-with-4d-bim-modelling\\\/\"]}]},{\"@type\":\"ImageObject\",\"inLanguage\":\"de-DE\",\"@id\":\"https:\\\/\\\/www.mercuryeng.com\\\/de\\\/2022\\\/07\\\/13\\\/optimizing-data-centre-project-planning-with-4d-bim-modelling\\\/#primaryimage\",\"url\":\"\\\/wp-content\\\/uploads\\\/2022\\\/07\\\/feature-1.jpg\",\"contentUrl\":\"\\\/wp-content\\\/uploads\\\/2022\\\/07\\\/feature-1.jpg\",\"width\":1400,\"height\":933,\"caption\":\"Stock photo: Mercury staff viewing a Building Information Model of metal structure.\"},{\"@type\":\"BreadcrumbList\",\"@id\":\"https:\\\/\\\/www.mercuryeng.com\\\/de\\\/2022\\\/07\\\/13\\\/optimizing-data-centre-project-planning-with-4d-bim-modelling\\\/#breadcrumb\",\"itemListElement\":[{\"@type\":\"ListItem\",\"position\":1,\"name\":\"Home\",\"item\":\"https:\\\/\\\/www.mercuryeng.com\\\/de\\\/\"},{\"@type\":\"ListItem\",\"position\":2,\"name\":\"Optimizing data centre project planning with 4D BIM modelling\"}]},{\"@type\":\"WebSite\",\"@id\":\"https:\\\/\\\/www.mercuryeng.com\\\/de\\\/#website\",\"url\":\"https:\\\/\\\/www.mercuryeng.com\\\/de\\\/\",\"name\":\"Mercury Engineering\",\"description\":\"Ihre Vision, unsere Verpflichtung.\",\"potentialAction\":[{\"@type\":\"SearchAction\",\"target\":{\"@type\":\"EntryPoint\",\"urlTemplate\":\"https:\\\/\\\/www.mercuryeng.com\\\/de\\\/?s={search_term_string}\"},\"query-input\":{\"@type\":\"PropertyValueSpecification\",\"valueRequired\":true,\"valueName\":\"search_term_string\"}}],\"inLanguage\":\"de-DE\"},{\"@type\":\"Person\",\"@id\":\"https:\\\/\\\/www.mercuryeng.com\\\/de\\\/#\\\/schema\\\/person\\\/523c7a8c2fb2021a9ac2a44d26c5920e\",\"name\":\"Tiffany Zhou\",\"image\":{\"@type\":\"ImageObject\",\"inLanguage\":\"de-DE\",\"@id\":\"https:\\\/\\\/secure.gravatar.com\\\/avatar\\\/35455f4c435d8a152841ca8a4b4cbb5e40cb6c84b96a7da207d95760aca3c790?s=96&d=mm&r=g\",\"url\":\"https:\\\/\\\/secure.gravatar.com\\\/avatar\\\/35455f4c435d8a152841ca8a4b4cbb5e40cb6c84b96a7da207d95760aca3c790?s=96&d=mm&r=g\",\"contentUrl\":\"https:\\\/\\\/secure.gravatar.com\\\/avatar\\\/35455f4c435d8a152841ca8a4b4cbb5e40cb6c84b96a7da207d95760aca3c790?s=96&d=mm&r=g\",\"caption\":\"Tiffany Zhou\"},\"url\":\"https:\\\/\\\/www.mercuryeng.com\\\/de\\\/author\\\/tzhou\\\/\"}]}<\/script>\n<!-- \/ Yoast SEO plugin. -->","yoast_head_json":{"title":"Optimizing data centre project planning with 4D BIM modelling","description":"Mercury delivered two data centre projects while utilizing 4D BIM modeling, enabling us to optimize project planning and eliminate risks.","robots":{"index":"index","follow":"follow","max-snippet":"max-snippet:-1","max-image-preview":"max-image-preview:large","max-video-preview":"max-video-preview:-1"},"canonical":"https:\/\/www.mercuryeng.com\/de\/2022\/07\/13\/optimizing-data-centre-project-planning-with-4d-bim-modelling\/","og_locale":"de_DE","og_type":"article","og_title":"Optimizing data centre project planning with 4D BIM modelling","og_description":"Mercury recently delivered two data centre projects, while utilizing 4D BIM modeling, enabling our team to optimize project planning, while eliminating potential risks from outset.","og_url":"https:\/\/www.mercuryeng.com\/de\/2022\/07\/13\/optimizing-data-centre-project-planning-with-4d-bim-modelling\/","og_site_name":"Mercury Engineering","article_published_time":"2022-07-13T10:34:34+00:00","article_modified_time":"2022-07-13T10:42:47+00:00","og_image":[{"width":1430,"height":953,"url":"https:\/\/www.mercuryeng.com\/wp-content\/uploads\/2022\/07\/feature-1.jpg","type":"image\/jpeg"}],"author":"Tiffany Zhou","twitter_card":"summary_large_image","twitter_title":"Optimizing data centre project planning with 4D BIM modelling","twitter_description":"Mercury recently delivered two data centre projects, while utilizing 4D BIM modeling, enabling our team to optimize project planning, while eliminating potential risks from outset.","twitter_image":"https:\/\/www.mercuryeng.com\/wp-content\/uploads\/2022\/07\/feature-1.jpg","twitter_misc":{"Verfasst von":"Tiffany Zhou","Gesch\u00e4tzte Lesezeit":"2 Minuten"},"schema":{"@context":"https:\/\/schema.org","@graph":[{"@type":"Article","@id":"https:\/\/www.mercuryeng.com\/de\/2022\/07\/13\/optimizing-data-centre-project-planning-with-4d-bim-modelling\/#article","isPartOf":{"@id":"https:\/\/www.mercuryeng.com\/de\/2022\/07\/13\/optimizing-data-centre-project-planning-with-4d-bim-modelling\/"},"author":{"name":"Tiffany Zhou","@id":"https:\/\/www.mercuryeng.com\/de\/#\/schema\/person\/523c7a8c2fb2021a9ac2a44d26c5920e"},"headline":"Optimizing data centre project planning with 4D BIM modelling","datePublished":"2022-07-13T10:34:34+00:00","dateModified":"2022-07-13T10:42:47+00:00","mainEntityOfPage":{"@id":"https:\/\/www.mercuryeng.com\/de\/2022\/07\/13\/optimizing-data-centre-project-planning-with-4d-bim-modelling\/"},"wordCount":403,"image":{"@id":"https:\/\/www.mercuryeng.com\/de\/2022\/07\/13\/optimizing-data-centre-project-planning-with-4d-bim-modelling\/#primaryimage"},"thumbnailUrl":"\/wp-content\/uploads\/2022\/07\/feature-1.jpg","articleSection":["News","Design, Quality &amp; Innovation"],"inLanguage":"de-DE"},{"@type":"WebPage","@id":"https:\/\/www.mercuryeng.com\/de\/2022\/07\/13\/optimizing-data-centre-project-planning-with-4d-bim-modelling\/","url":"https:\/\/www.mercuryeng.com\/de\/2022\/07\/13\/optimizing-data-centre-project-planning-with-4d-bim-modelling\/","name":"Optimizing data centre project planning with 4D BIM modelling","isPartOf":{"@id":"https:\/\/www.mercuryeng.com\/de\/#website"},"primaryImageOfPage":{"@id":"https:\/\/www.mercuryeng.com\/de\/2022\/07\/13\/optimizing-data-centre-project-planning-with-4d-bim-modelling\/#primaryimage"},"image":{"@id":"https:\/\/www.mercuryeng.com\/de\/2022\/07\/13\/optimizing-data-centre-project-planning-with-4d-bim-modelling\/#primaryimage"},"thumbnailUrl":"\/wp-content\/uploads\/2022\/07\/feature-1.jpg","datePublished":"2022-07-13T10:34:34+00:00","dateModified":"2022-07-13T10:42:47+00:00","author":{"@id":"https:\/\/www.mercuryeng.com\/de\/#\/schema\/person\/523c7a8c2fb2021a9ac2a44d26c5920e"},"description":"Mercury delivered two data centre projects while utilizing 4D BIM modeling, enabling us to optimize project planning and eliminate risks.","breadcrumb":{"@id":"https:\/\/www.mercuryeng.com\/de\/2022\/07\/13\/optimizing-data-centre-project-planning-with-4d-bim-modelling\/#breadcrumb"},"inLanguage":"de-DE","potentialAction":[{"@type":"ReadAction","target":["https:\/\/www.mercuryeng.com\/de\/2022\/07\/13\/optimizing-data-centre-project-planning-with-4d-bim-modelling\/"]}]},{"@type":"ImageObject","inLanguage":"de-DE","@id":"https:\/\/www.mercuryeng.com\/de\/2022\/07\/13\/optimizing-data-centre-project-planning-with-4d-bim-modelling\/#primaryimage","url":"\/wp-content\/uploads\/2022\/07\/feature-1.jpg","contentUrl":"\/wp-content\/uploads\/2022\/07\/feature-1.jpg","width":1400,"height":933,"caption":"Stock photo: Mercury staff viewing a Building Information Model of metal structure."},{"@type":"BreadcrumbList","@id":"https:\/\/www.mercuryeng.com\/de\/2022\/07\/13\/optimizing-data-centre-project-planning-with-4d-bim-modelling\/#breadcrumb","itemListElement":[{"@type":"ListItem","position":1,"name":"Home","item":"https:\/\/www.mercuryeng.com\/de\/"},{"@type":"ListItem","position":2,"name":"Optimizing data centre project planning with 4D BIM modelling"}]},{"@type":"WebSite","@id":"https:\/\/www.mercuryeng.com\/de\/#website","url":"https:\/\/www.mercuryeng.com\/de\/","name":"Mercury Engineering","description":"Ihre Vision, unsere Verpflichtung.","potentialAction":[{"@type":"SearchAction","target":{"@type":"EntryPoint","urlTemplate":"https:\/\/www.mercuryeng.com\/de\/?s={search_term_string}"},"query-input":{"@type":"PropertyValueSpecification","valueRequired":true,"valueName":"search_term_string"}}],"inLanguage":"de-DE"},{"@type":"Person","@id":"https:\/\/www.mercuryeng.com\/de\/#\/schema\/person\/523c7a8c2fb2021a9ac2a44d26c5920e","name":"Tiffany Zhou","image":{"@type":"ImageObject","inLanguage":"de-DE","@id":"https:\/\/secure.gravatar.com\/avatar\/35455f4c435d8a152841ca8a4b4cbb5e40cb6c84b96a7da207d95760aca3c790?s=96&d=mm&r=g","url":"https:\/\/secure.gravatar.com\/avatar\/35455f4c435d8a152841ca8a4b4cbb5e40cb6c84b96a7da207d95760aca3c790?s=96&d=mm&r=g","contentUrl":"https:\/\/secure.gravatar.com\/avatar\/35455f4c435d8a152841ca8a4b4cbb5e40cb6c84b96a7da207d95760aca3c790?s=96&d=mm&r=g","caption":"Tiffany Zhou"},"url":"https:\/\/www.mercuryeng.com\/de\/author\/tzhou\/"}]}},"_links":{"self":[{"href":"https:\/\/www.mercuryeng.com\/de\/wp-json\/wp\/v2\/posts\/8600","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/www.mercuryeng.com\/de\/wp-json\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/www.mercuryeng.com\/de\/wp-json\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/www.mercuryeng.com\/de\/wp-json\/wp\/v2\/users\/17"}],"replies":[{"embeddable":true,"href":"https:\/\/www.mercuryeng.com\/de\/wp-json\/wp\/v2\/comments?post=8600"}],"version-history":[{"count":0,"href":"https:\/\/www.mercuryeng.com\/de\/wp-json\/wp\/v2\/posts\/8600\/revisions"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/www.mercuryeng.com\/de\/wp-json\/wp\/v2\/media\/8602"}],"wp:attachment":[{"href":"https:\/\/www.mercuryeng.com\/de\/wp-json\/wp\/v2\/media?parent=8600"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/www.mercuryeng.com\/de\/wp-json\/wp\/v2\/categories?post=8600"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}