Enterprise Data Centres

AMS15 Data Centre, Amsterdam, Netherlands

Mercury was commissioned by this client to provide a turnkey Construction service for their new flagship 60,000sqft Data Centre at Hoofdoorp, Amsterdam in the Netherlands. The project commenced in July 2016 and Phase 1handover occurred in May 2017.

The scope of work consisted of constructing a new facility on a Greenfield site. The facility has a planned IT Capacity of 60,000sqft over 6 Halls at a power density of 2kw/Sq.m
The project Management and Execution team comprised of highly experienced Mercury Management supported by both local and International supply chain of specialist consultants, vendors and sub-contractors.

Our Prime sub-contractor was BAM BV who were contracted to carry out all of the CSA work including all Piling, Steelwork, new Roof and Site fencing.

SERVICES
Contracting
  • Amsterdam,Netherlands
  • 6 months
  • Confidential
  • €25,500,000